EVALUASI KINERJA ALAT PENUKAR KALOR AIR PREHEATER TIPE ROTARY LAP 10320/2200 UNIT 2 PT PLN ( PERSERO ) SPP PLTU I JAWA TENGAH REMBANG ( PERFORMANCE EVALUATION HEAT EXCHANGER AIR PREHEATER ROTARY TYPE LAP 10320/2200 IN UNIT 2 OF PT PLN ( PERSERO ) SPP PLTU I JAWA TENGAH REMBANG )

Mahatma, Wahyu Arief and Darmanto, Seno (2013) EVALUASI KINERJA ALAT PENUKAR KALOR AIR PREHEATER TIPE ROTARY LAP 10320/2200 UNIT 2 PT PLN ( PERSERO ) SPP PLTU I JAWA TENGAH REMBANG ( PERFORMANCE EVALUATION HEAT EXCHANGER AIR PREHEATER ROTARY TYPE LAP 10320/2200 IN UNIT 2 OF PT PLN ( PERSERO ) SPP PLTU I JAWA TENGAH REMBANG ). Undergraduate thesis, D3 Kerjasama PT. PLN - Fakultas Teknik Bidang Mesin.

[img]
Preview
PDF
789Kb
[img]
Preview
PDF
95Kb
[img]
Preview
PDF
156Kb
[img]PDF
Restricted to Repository staff only

855Kb
[img]PDF
Restricted to Repository staff only

502Kb
[img]
Preview
PDF
88Kb

Abstract

Kebutuhan pemanasan awal untuk udara pembakaran pada boiler sekarang ini menjadi suatu keharusan sebagai usaha untuk meningkatkan efisiensi boiler. Rotary air preheater digunakan untuk pemanasan awal (preheater) pada saat pembakaran di dalam ruang bakar terjadi, khususnya pada Pembangkit Listrik Tenaga Uap (PLTU). Udara pembakaran yang dibutuhkan di ruang bakar diharapkan memiliki temperatur yang lebih tinggi agar menghasilkan pembakaran yang lebih sempurna. Apabila air preheater dioperasikan beberapa waktu, maka akan terjadi penurunan unjuk kerja dari alat tersebut. Penurunan unjuk kerja bisa jadi disebabkan oleh terbentuknya kerak, korosi, kebocoran (leakage) maupun aliran fluida yang menyebabkan friksi terhadap dinding alat Tujuan dari evaluasi ini adalah membandingkan seberapa besar penurunan kinerja air preheater dari awal operasi (November 2010) dengan waktu operasi aktual (Februari 2013) pada beban 215 MW dan 300 MW. Dalam kasus ini Efisiensi air preheater pada bulan November 2011 sampai Februari 2013 dengan beban 215 MW mengalami penurunan sebesar 5,06 % pada APH A, dan 7,11 % pada APH B. Efisiensi air preheater pada bulan November 2011 sampai Februari 2013 dengan beban 300 MW mengalami penurunan sebesar 6,62 % pada APH A, dan 7,9 % pada APH B. Hal ini menunjukkan jumlah panas yang hilang terus meningkat karena terbentuknya kerak di permukaan plat perpindahan panas, penurunan tekanan, dan kebocoran udara, sehinggga proses perpindahan panas yang terjadi belum bisa optimal. Kata kunci : perpindahan panas, air preheater, efisiensi The need for combustion air preheating the boiler now become a necessity in an attempt to improve the efficiency of the boiler. Rotary air pre-heater is used to preheat (preheater) during combustion in the combustion chamber occurs, especially in Steam Power Plant (CPP). Required combustion air in the combustion chamber is expected to have a higher temperature in order to produce a more complete combustion. If water preheater operated some time, there will be a decline in the performance of these tools. Decline in performance could be due to scaling, corrosion, leakage (leakage) as well as fluid flow that causes friction against the wall plate. The purpose of this evaluation is to compare how much water preheater performance degradation of initial operation (November 2010) with the actual operating time (February 2013) on the load 215 MW and 300 MW. In this case the efficiency of water preheater in November 2011 to February 2013 with a load of 215 MW has decreased by 5.06% on APH A, and 7.11% at APH B. Water efficiency preheater in November 2011 to February 2013 with a load of 300 MW has decreased by 6.62% on APH A, and 7.9% at APH B. This indicates the amount of heat lost due to increased formation of a crust on the surface of the plate heat transfer, pressure drop, and leak air, so as the heat transfer processes that occur can not be optimal. Keywords: heat transfer, air preheater, efficiency

Item Type:Thesis (Undergraduate)
Subjects:T Technology > TJ Mechanical engineering and machinery
Divisions:Faculty of Engineering > Diploma in Mechanical Engineering
Faculty of Engineering > Diploma in Mechanical Engineering
ID Code:41150
Deposited By:INVALID USER
Deposited On:20 Dec 2013 08:48
Last Modified:20 Dec 2013 08:48

Repository Staff Only: item control page